Key takeaways
- The top-up is for connections registered under Mukhyamantri Nishulk Bijli Yojana (MNBY), the 150-free-units scheme.
- It is paid through your DISCOM after the central subsidy lands, to the same bank account.
- A 1.1 kW plant sized to 150 units a month can come to almost nothing after both subsidies.
- Larger plants take the full ₹95,000; the top-up does not shrink because you went bigger.
Where the ₹17,000 comes from
Mukhyamantri Nishulk Bijli Yojana gives eligible Rajasthan households 150 free units a month. The state's plan is to move those households onto rooftop solar so the free units come from their own roofs rather than from the DISCOM's purchase bill. The top-up of up to ₹17,000, on top of the central subsidy, is the incentive to make that move.
Who qualifies
- Your connection is registered under MNBY. If your bill already shows the 150-unit concession, you are in the frame.
- The plant is a grid-connected PM Surya Ghar installation on that same connection, built by a vendor registered with your DISCOM.
- The central subsidy has been approved; the top-up follows it.
- Eligibility is by connection, not by promise. We check yours against the DISCOM record before we file, so nobody is sized for a subsidy they will not get.
How it is paid
- The central subsidy is credited first, by direct transfer from the national portal, typically 30 to 90 days after commissioning.
- The state top-up follows, paid through your DISCOM (JVVNL, AVVNL or JdVVNL) to the same Aadhaar-linked account.
- We track both and tell you on WhatsApp as each one lands.
The maths for a 1.1 kW plant
The scheme was designed around a plant that covers 150 units a month, which in the scheme's own sizing is about 1.1 kW. The central subsidy is ₹30,000 per kW up to 2 kW, so it is paid pro rata on that size.
| Line | Amount |
|---|---|
| Central subsidy on 1.1 kW, at ₹30,000 per kW | ₹33,000 |
| Rajasthan top-up | up to ₹17,000 |
| Total subsidy | up to ₹50,000 |
Set against the price of a 1.1 kW plant, this is why the state says the plant can come to almost nothing. The exact net figure depends on the price card and is quoted on WhatsApp.
At 2 kW or 3 kW the central subsidy rises to ₹60,000 and ₹78,000, the top-up stays, and the total reaches ₹95,000 at 3 kW. Most families whose bill runs above the free units find the 2 or 3 kW pack pays back faster. See how many units a 3 kW plant makes.
The catches
- One subsidy per connection. If a connection has already drawn a rooftop subsidy, neither the central nor the state amount applies.
- Vendor registration with your DISCOM is a hard requirement; work by an unregistered installer gets nothing.
- The bank account must be Aadhaar-seeded, or both transfers fail quietly.
- The scheme window: the last day to avail the subsidy is 31 March 2027. The PM Surya Ghar page keeps the slabs and the deadline current.
Part of PM Surya Ghar subsidy in Rajasthan
Suntask engineering desk · Jaipur
Posts are drafted by the engineers who size, file and install Suntask plants across Rajasthan, and checked against the scheme portals before publishing. Figures carry the date they were last checked.